INFO #3 : Nuclear Fuel Cycle [IAEA]

The Nuclear Fuel Cycle


  • The nuclear fuel cycle is the series of industrial processes which involve the production of electricity from uranium in nuclear power reactors. 
  • Uranium is a relatively common element that is found throughout the world. It is mined in a number of countries and must be processed before it can be used as fuel for a nuclear reactor. 
  • Fuel removed from a reactor, after it has reached the end of its useful life, can be reprocessed to produce new fuel. 
The various activities associated with the production of electricity from nuclear reactions are referred to collectively as the nuclear fuel cycle. The nuclear fuel cycle starts with the mining of uranium and ends with the disposal of nuclear waste. With the reprocessing of used fuel as an option for nuclear energy, the stages form a true cycle.
The Nuclear Fuel Cycle 

Uranium

Uranium is a slightly radioactive metal that occurs throughout the Earth's crust (see page on Uranium and Depleted Uranium). It is about 500 times more abundant than gold and about as common as tin. It is present in most rocks and soils as well as in many rivers and in sea water. It is, for example, found in concentrations of about four parts per million (ppm) in granite, which makes up 60% of the Earth's crust. In fertilisers, uranium concentration can be as high as 400 ppm (0.04%), and some coal deposits contain uranium at concentrations greater than 100 ppm (0.01%). Most of the radioactivity associated with uranium in nature is in fact due to other minerals derived from it by radioactive decay processes, and which are left behind in mining and milling.
There are a number of areas around the world where the concentration of uranium in the ground is sufficiently high that extraction of it for use as nuclear fuel is economically feasible. Such concentrations are called ore.
Uranium mining
Both excavation and in situ techniques are used to recover uranium ore. Excavation may be underground and open pit mining.
In general, open pit mining is used where deposits are close to the surface and underground mining is used for deep deposits, typically greater than 120 m deep. Open pit mines require large holes on the surface, larger than the size of the ore deposit, since the walls of the pit must be sloped to prevent collapse. As a result, the quantity of material that must be removed in order to access the ore may be large. Underground mines have relatively small surface disturbance and the quantity of material that must be removed to access the ore is considerably less than in the case of an open pit mine. Special precautions, consisting primarily of increased ventilation, are required in underground mines to protect against airborne radiation exposure.
An increasing proportion of the world's uranium now comes from in situ leach (ISL) mining, where oxygenated groundwater is circulated through a very porous orebody to dissolve the uranium oxide and bring it to the surface. ISL may be with slightly acid or with alkaline solutions to keep the uranium in solution. The uranium oxide is then recovered from the solution as in a conventional mill.
The decision as to which mining method to use for a particular deposit is governed by the nature of the orebody, safety and economic considerations.
For more detailed information see the information pages on:

Uranium milling

Milling, which is generally carried out close to a uranium mine, extracts the uranium from the ore. Most mining facilities include a mill, although where mines are close together, one mill may process the ore from several mines. Milling produces a uranium oxide concentrate which is shipped from the mill. It is sometimes referred to as 'yellowcake' and generally contains more than 80% uranium. The original ore may contain as little as 0.1% uranium, or even less.
In a mill, uranium is extracted from the crushed and ground-up ore by leaching, in which either a strong acid or a strong alkaline solution is used to dissolve the uranium oxide. The uranium oxide is then precipitated and removed from the solution. After drying and usually heating it is packed in 200-litre drums as a concentrate, sometimes referred to as 'yellowcake'.
The remainder of the ore, containing most of the radioactivity and nearly all the rock material, becomes tailings, which are emplaced in engineered facilities near the mine (often in mined out pit). Tailings need to be isolated from the environment because they contain long-lived radioactive materials in low concentrations and toxic materials such as heavy metals; however, the total quantity of radioactive elements is less than in the original ore, and their collective radioactivity will be much shorter-lived.

Conversion and enrichment

The uranium oxide product of a uranium mill is not directly usable as a fuel for a nuclear reactor and additional processing is required. Only 0.7% of natural uranium is 'fissile', or capable of undergoing fission, the process by which energy is produced in a nuclear reactor. The form, or isotope, of uranium which is fissile is the uranium-235 (U-235) isotope. The remainder is uranium-238 (U-238). For most kinds of reactor, the concentration of the fissile uranium-235 isotope needs to be increased – typically to between 3.5% and 5% U-235. This is done by a process known as enrichment, which requires the uranium to be in a gaseous form. The uranium oxide concentrate is therefore first converted to uranium hexafluoride, which is a gas at relatively low temperatures.
At a conversion facility, the uranium oxide is first refined to uranium dioxide, which can be used as the fuel for those types of reactors that do not require enriched uranium. Most is then converted into uranium hexafluoride, ready for the enrichment plant. The main hazard of this stage of the fuel cycle is the use of hydrogen fluoride. The uranium hexafluoride is then drained into 14-tonne cylinders where it solidifies. These strong metal containers are shipped to the enrichment plant.
The enrichment process separates gaseous uranium hexafluoride into two streams, one being enriched to the required level and known as low-enriched uranium; the other stream is progressively depleted in U-235 and is called 'tails', or simply depleted uranium.
There are two enrichment processes in large-scale commercial use, each of which uses uranium hexafluoride gas as feed: diffusion and centrifuge. These processes both use the physical properties of molecules, specifically the 1% mass difference between the two uranium isotopes, to separate them. The last diffusion enrichment plants are likely to be phased out by 2013.
The product of this stage of the nuclear fuel cycle is enriched uranium hexafluoride, which is reconverted to produce enriched uranium oxide. Up to this point the fuel material can be considered fungible (though enrichment levels vary), but fuel fabrication involves very specific design.
Enrichment is covered in detail in the page on Uranium Enrichment.

Fuel fabrication

Reactor fuel is generally in the form of ceramic pellets. These are formed from pressed uranium oxide (UO2) which is sintered (baked) at a high temperature (over 1400°C)a. The pellets are then encased in metal tubes to form fuel rods, which are arranged into a fuel assembly ready for introduction into a reactor. The dimensions of the fuel pellets and other components of the fuel assembly are precisely controlled to ensure consistency in the characteristics of the fuel.
In a fuel fabrication plant great care is taken with the size and shape of processing vessels to avoid criticality (a limited chain reaction releasing radiation). With low-enriched fuel criticality is most unlikely, but in plants handling special fuels for research reactors this is a vital consideration.

Power generation and burn-up

Inside a nuclear reactor the nuclei of U-235 atoms split (fission) and, in the process, release energy. This energy is used to heat water and turn it into steam. The steam is used to drive a turbine connected to a generator which produces electricity. Some of the U-238 in the fuel is turned into plutonium in the reactor core. The main plutonium isotope is also fissile and this yields about one third of the energy in a typical nuclear reactor. The fissioning of uranium (and the plutonium generated in situ) is used as a source of heat in a nuclear power station in the same way that the burning of coal, gas or oil is used as a source of heat in a fossil fuel power plant.
Typically, some 44 million kilowatt-hours of electricity are produced from one tonne of natural uranium. The production of this amount of electrical power from fossil fuels would require the burning of over 20,000 tonnes of black coal or 8.5 million cubic metres of gas.
An issue in operating reactors and hence specifying the fuel for them is fuel burn-up. This is measured in gigawatt-days per tonne and its potential is proportional to the level of enrichment. Hitherto a limiting factor has been the physical robustness of fuel assemblies, and hence burn-up levels of about 40 GWd/t have required only around 4% enrichment. But with better equipment and fuel assemblies, 55 GWd/t is possible (with 5% enrichment), and 70 GWd/t is in sight, though this would require 6% enrichment. The benefit of this is that operation cycles can be longer – around 24 months – and the number of fuel assemblies discharged as used fuel can be reduced by one third. Associated fuel cycle cost is expected to be reduced by about 20%.
As with as a coal-fired power station about two thirds of the heat is dumped, either to a large volume of water (from the sea or large river, heating it a few degrees) or to a relatively smaller volume of water in cooling towers, using evaporative cooling (latent heat of vapourisation).

Used fuel

With time, the concentration of fission fragments and heavy elements formed in the same way as plutonium in the fuel will increase to the point where it is no longer practical to continue to use the fuel. So after 12-24 months the 'spent fuel' is removed from the reactor. The amount of energy that is produced from a fuel bundle varies with the type of reactor and the policy of the reactor operator.
When removed from a reactor, the fuel will be emitting both radiation, principally from the fission fragments, and heat. Used fuel is unloaded into a storage pond immediately adjacent to the reactor to allow the radiation levels to decrease. In the ponds the water shields the radiation and absorbs the heat. Used fuel is held in such pools for several months to several years. It may be transferred to ventilated dry storage on site. 
Depending on policies in particular countries, some used fuel may be transferred to central storage facilities. Ultimately, used fuel must either be reprocessed or prepared for permanent disposal.

Reprocessing

Used fuel is about 94% U-238 but it also contains almost 1% U-235 that has not fissioned, almost 1% plutonium and 4.5% fission products, which are highly radioactive, with other transuranic elements formed in the reactor. In a reprocessing facility the used fuel is separated into its three components: uranium, plutonium and waste, which contains fission products. Reprocessing enables recycling of the uranium and plutonium into fresh fuel, and produces a significantly reduced amount of waste (compared with treating all used fuel as waste). See page on Processing of Used Nuclear Fuel.

Uranium and plutonium recycling

The uranium from reprocessing, which typically contains a slightly higher concentration of U-235 than occurs in nature, can be reused as fuel after conversion and enrichment.
The plutonium can be directly made into mixed oxide (MOX) fuel, in which uranium and plutonium oxides are combined. In reactors that use MOX fuel, plutonium substitutes for the U-235 in normal uranium oxide fuel (see page on Mixed Oxide (MOX) Fuel).

Used fuel disposal

At the present time, there are no disposal facilities (as opposed to storage facilities) in operation in which used fuel, not destined for reprocessing, and the waste from reprocessing, can be placed. Although technical issues related to disposal have been addressed, there is currently no pressing technical need to establish such facilities, as the total volume of such wastes is relatively small. Further, the longer it is stored the easier it is to handle, due to the progressive diminution of radioactivity. There is also a reluctance to dispose of used fuel because it represents a significant energy resource which could be reprocessed at a later date to allow recycling of the uranium and plutonium. There is also a proposal to use it in Candu reactors directly as fuel. This proposal, known as DUPIC (direct use of used PWR fuel in Candu reactors) is covered at the end of the page on Processing of Used Nuclear Fuel.
A number of countries are carrying out studies to determine the optimum approach to the disposal of used fuel and wastes from reprocessing. The general consensus favours its placement into deep geological repositories, initially recoverable before being permanently sealed.

Wastes

Wastes from the nuclear fuel cycle are categorised as high-, medium- or low-level wastes by the amount of radiation that they emit. These wastes come from a number of sources and include:
  • low-level waste produced at all stages of the fuel cycle;
  • intermediate-level waste produced during reactor operation and by reprocessing;
  • high-level waste, which is waste containing fission products from reprocessing, and in many countries, the used fuel itself.
The enrichment process leads to the production of much 'depleted' uranium, in which the concentration of U-235 is significantly less than the 0.7% found in nature. Small quantities of this material, which is primarily U-238, are used in applications where high density material is required, including radiation shielding and some is used in the production of MOX fuel. While U-238 is not fissile it is a low specific activity radioactive material and some precautions must, therefore, be taken in its storage or disposal.

Material balance in the nuclear fuel cycle

The following figures may be regarded as typical for the annual operation of a 1000 MWe nuclear power reactor:b 
Mining20,000 tonnes of 1% uranium ore
Milling230 tonnes of uranium oxide concentrate (which contains 195 tonnes of uranium)
Conversion288 tonnes uranium hexafluoride, UF6 (with 195 tU)
Enrichment35 tonnes enriched UF6 (containing 24 t enriched U) – balance is 'tails'
Fuel fabrication27 tonnes UO2 (with 24 t enriched U)
Reactor operation8760 million kWh (8.76 TWh) of electricity at full output, hence 22.3 tonnes of natural U per TWh
Used fuel27 tonnes containing 240 kg transuranics (mainly plutonium), 23 t uranium (0.8% U-235), 1100kg fission products.

Further information

Notes

a. UO2 has a very high melting point – 2865°C (compared with uranium metal – 1132°C). [Back]
b. Figures are based on the following assumptions: enrichment to 4% U-235 with 0.25% tails assay – hence 140,000 SWU (separative work units) of enrichment needed (one SWU requires about 50kWh of electricity at a gas centrifuge enrichment plant); core load 72 tU, refuelling so that 24 tU/yr is replaced; operation – 45,000 MWday/t (45 GWd/t) burn-up, 33% thermal efficiency. In fact, a 1000 MWe reactor cannot be expected to run at 100% load factor – 90% is more typical, so an output of around 7.75 TWh/yr is more realistic, but this simply means scaling back the inputs accordingly, e.g. to 175.5 tU.
Canadian figures for tU/GWe/yr suggest slightly lower uranium requirements and utilization for PHWRs than for light water reactors. An International Atomic Energy Agency technical report1 gives 157 tU at typical 7.5 GWd/t burn-up and 31% thermal efficiency, or 142 tU at 90% capacity factor, hence 80% of the input compared with a typical LWR above. This is 17.9 tU/TWh.
Considering just how much of the original uranium is actually used: 0.7% fissile U-235 is in natural U (Unat), on above figures 0.49% of Unat goes into fuel as the fissile part, 0.39% is actually fissioned, and in addition about half that much U-238 turned into Pu-239 is fissioned, giving about a 0.6% utilization of the original Unat. [Back]

References

1. Heavy Water Reactors: Status and Projected Development, Technical Reports Series No. 407, International Atomic Energy Agency, 2002, STI/DOC/010/407 (ISBN: 9201115024). PHWR data is taken from Chapter 6, HWR Fuel Cycles [Back]

credit to : www.iaea.org

Wednesday, October 6, 2010

Post-Chernobyl Global Co-operation: 5 Years Later

credit to : (Article in IAEA Newsbriefs, Vol. 6, No.2 (49), March/April 1991)

In the five years since the Chernobyl nuclear plant accident in April 1986, governments working through the 1AEA and other international organizations have reinforced their cooperation in areas of nuclear safety and radiological protection. Key achievements cover areas including:

  • Post-Accident Analysis And Review. The Chernobyl accident's causes, consequences, and radiological impact have been thoroughly analyzed by international experts. In August 1986, more than 600 participants met at a post-accident review conference of the IAEA; a concluding summary report attributed the accident mainly to flagrant disregard by operating personnel of safety rules and procedures that placed the reactor in an unstable state resulting in an explosion. In view of design characteristics peculiar to the Chernobyl type of reactor, a limited number of which are operating only in the Soviet Union, the accident did not call into question the design or safety of the world's other types of nuclear plants. Chernobyl's immediate consequences were severe - the accident destroyed the plant, killed 31 workers and fire-fighters, seriously injured nearly 300 workers, and released a great amount of radioactive material that severely contaminated a large area around the plant. The radiological impact was assessed in 1988 by the United Nations Scientific Committee on the Effects of Atomic Radiation (UNSCEAR). In Byelorussia, among the most heavily affected areas, UNSCEAR found that the highest average dose a person sustained in the first year after the accident was about equal to that due to I year's exposure to natural background radiation. Outside the USSR, this dose was about a third of that received in a year from natural background radiation.

    The situation in the most heavily affected Soviet republics -- Byelorussia, Russia, and the Ukraine -- continues to command international attention. In response to concerns of Soviet citizens living there, USSR authorities in late 1989 requested the IAEA to coordinate an international assessment of Chernobyl's health and radiological consequences, and to review Soviet countermeasures to protect public health and safety. Results of that assessment, which involves UNSCEAR, the World Health Organization (WHO), and other organizations, will be published in May 1991. Separately, assistance projects have been initiated by UN bodies including WHO and the United Nations Scientific, Educational and Cultural Organization (UNESCO).

  • Plant Safety Reviews And Technical Exchanges. More countries are inviting teams of international experts to review the operational safety of their nuclear plants. As before the Chernobyl accident, national regulators and utilities carry the primary responsibility for the safety of their country's nuclear plants: no supranational safety authority has been formed. But to complement national efforts and to visibly reinforce them, governments are using international safety services expanded or created over the past 5 years. Under one IAEA programme, 37 missions to plants in more than 20 countries have been conducted since 1986. An interrelated project is placing special emphasis on design and operational reviews of older nuclear plants, currently WWER-440/230 units operating in Eastern Europe and the Soviet Union. Ten reactors of this type have been selected for on-site reviews in 1991.

    Operational experience, training methods, and safety practices also are being more widely shared by nuclear utilities through a programme of technical exchange visits coordinated by the World Association of Nuclear Operators (WANO), a non-governmental organization that nuclear utilities formed after the Chernobyl accident. Since September 1989, some 50 exchanges involving nuclear plant operating personnel from Western countries, the USSR, and Eastern Europe have been coordinated.

  • Event Analysis And Safety Assessment. Global collaboration to prevent serious nuclear plant accidents includes greater use of resources for analyzing and sharing technical details about unusual events that have occurred. Under a project initiated in 1986, fourteen IAEA expert missions have assisted nuclear authorities in nine countries with such safety assessments. Mission experts specifically review the root causes of past significant incidents and accidents, and the effectiveness of corrective actions, making recommendations as needed. Through another post-Chernobyl IAEA programme started in 1989, six countries have requested international peer reviews of nuclear plant safety studies they have done using the methodology of probabilistic safety assessment; others have requested help in conducting such studies as part of comprehensive plant safety reviews.

    National nuclear authorities also are exchanging more reports on safety-significant events at nuclear plants through a computerized global Incident Reporting System (IRS). Operated since 1983 by the IAEA and Nuclear Energy Agency of the Organisation for Economic Co-operation and Development (NEA/OECD) to supplement national and regional systems, the IRS was upgraded after the Chernobyl accident to improve capabilities for collecting, analyzing, and disseminating information.

  • Emergency Notification And Assistance. A global system is in place to ensure the prompt reporting of nuclear accidents having potential transboundary consequences and to coordinate provision of technical and medical assistance in emergencies. More than 70 IAEA Member States have signed two international conventions that were drafted and adopted within 5 months of the Chernobyl accident: the Convention on the Early Notification of a Nuclear Accident and the Convention on Assistance in the Case of a Nuclear Accident or Radiological Emergency. The IAEA, which is the depositary of these conventions, started operating an Emergency Response System (ERS) in January 1989 to receive and pass on reported information, including radiological data, to governmental authorities, and to help coordinate assistance if required. ERS is supported by the Global Telecommunication System of the World Meteorological Organization (WMO). Since the Chernobyl accident in 1986, no nuclear plant accident has occurred that required international notification or assistance.

  • Supporting Health And Environmental Networks. Other global networks are supporting efforts to strengthen national capabilities for preventing and responding to radiological emergencies. They include the Radiation Emergency Medical Preparedness and Assistance Network of the World Health Organization (WHO), which is being developed among WHO's regional collaborating centres. Another is the Global Environmental Radiation Monitoring Network that was set up jointly with the United Nations Environment Programme (UNEP) to buttress data capabilities covering radioactivity levels in air, soil, and precipitation. Also in place, and expanded over the last 5 years, are IAEA radiation protection services tailored to the practical needs of developing countries. Under one service in which WHO participates, more than 40 countries have requested advisory missions since 1986 to establish or improve their radiation protection programmes.

    Permissible radioactivity levels for foodstuffs in international trade also have been issued. The Codex Alimentarius Commission of WHO and the Food and Agriculture Organization (FAO), using the IAEA's expertise and advice, adopted recommended levels in 1989. These global guidelines should help to prevent repetition of what happened in 1986, when national governments set widely varying levels that confused people and undermined their confidence in authorities.

  • Liability For Nuclear Damage. Legal experts from more than 50 countries are heading efforts to establish a more equitable and adequate international regime for compensation of victims in the event of a nuclear accident. In 1988, countries adopted a joint protocol to expand the scope of application of the two existing international conventions on civil liability for nuclear damage, which are wider auspices of the IAEA and NEA/OECD. Issues related to international civil and State liability, including possible revision of the existing conventions, remain under discussion.

  • Event Reporting. A standardized global approach has been developed for rapidly and clearly informing people about the significance of nuclear accidents. Twenty-seven countries are now using this International Nuclear Event Scale on a trial basis. Modelled on national systems, the scale uses seven levels to categorize a nuclear event, based on the extent of radiological effects and the performance of the plant's emergency safety systems and structures: for example, a major nuclear accident, such as Chernobyl, is Level 7, whereas an operational or functional anomaly at a nuclear plant is Level 1. Events are analyzed and categorized by national authorities in participating countries. The scale was developed in 1990 by the IAEA and NEA/OECD in cooperation with WANO.

  • Safety Codes And Principles. International safety recommendations for nuclear plants have been carefully reviewed and updated where required. international advisers to the IAEA's Nuclear Safety Standards Programme (NUSS) issued revised documents in 1988 that particularly reflect experience gained in accident prevention and management. NUSS, which includes some 60 codes and guides, covers areas such as nuclear plant construction, operation, and emergency planning. Basic safety principles for nuclear plants also were published in 1988 by the IAEA’s International Nuclear Safety Advisory Group (INSAG). The report responded to the need for a concise, integrated, and comprehensive statement of principles underlying advanced national policy and industry practices worldwide.